Stevenage Borough Council has agreed to start a new Local Plan, with a first consultation from 4 January to 15 February 2027. It aims to adopt the plan in September 2029.
Stevenage Borough Council is starting work on a new Local Plan, the document that decides where homes, jobs and roads go. Residents get their first say in a consultation from 4 January to 15 February 2027.
Updated 22 November: Cabinet approved the timetable and the notice of intention on 19 November, the decision notice shows. It gave the Director of Planning and Regulation authority to publish the scoping consultation and formally start the plan on 31 March 2027, and to change the timetable if needed.
The aim is to adopt the finished plan on 30 September 2029.
Why a new plan is needed
The current Stevenage Borough Local Plan runs from 2011 to 2031. It was adopted in May 2019, and a partial update, mainly on climate change, was adopted on 22 July 2026.
Its plan period ends in 2031. As that date gets closer, the plan’s policies carry less weight in planning decisions, the Cabinet report says.
The government has also changed how local plans are made. Each one now has to be prepared in 30 months, and government guidance sets deadlines for councils to start. The report says the proposed dates meet them.
The current plan’s targets are 7,600 homes and at least 140,000 square metres of employment space between 2011 and 2031. The new plan will set new figures for the years after 2031. None has been calculated yet.
The report flags a risk. Many of the current plan’s sites have been built or are being built, so the council may not have enough sites left to show a five-year supply of land for housing. A new housing figure would let it reset that.
The timetable
| Stage | Date |
|---|---|
| Notice of intention and timetable published | 26 November 2026 |
| Scoping consultation | 4 January to 15 February 2027 |
| Gateway 1: the 30-month clock starts | 31 March 2027 |
| Consultation on the plan’s contents and evidence | 16 June to 28 July 2027 |
| First check-in with the Planning Inspectorate | 6 December 2027 |
| Consultation on the draft plan | 26 June to 18 September 2028 |
| Second check-in with the Planning Inspectorate | 11 December 2028 |
| Submission to the government | 12 February 2029 |
| Public examination | Spring or summer 2029 |
| Adoption | 30 September 2029 |
The dates are from the council’s draft Local Plan timetable, which it says it will review every month.
Planning across the boundary
Stevenage is tightly bounded, so the report says its needs for homes, jobs and infrastructure “cannot be considered in isolation”. Its neighbouring councils have both started new Local Plans under the same rules.
Cabinet agreed to let officers set up joint working with those neighbours. It also agreed they should work with Hertfordshire County Council on a county-wide Spatial Development Strategy, and with the proposed Hertfordshire mayoral authority.
The plan could end up in other hands. Local government reorganisation is likely to come in a year later than first planned, the report says. So a plan adopted in September 2029 “may therefore fall to a successor authority”.
What it means for you
Nothing about where homes will go was decided on 19 November. The plan’s vision and policies come back to Cabinet in June 2027, before the second consultation.
The first chance to comment is the scoping consultation, from 4 January to 15 February 2027. It covers what the plan should deal with, how the council will involve people, and the environmental assessment. The report lists an online platform, drop-in sessions and workshops among the ways to take part.
North Hertfordshire’s own Local Plan consultation, covering Hitchin, Letchworth and Baldock, closes on 24 November.