The developer of Claxton House, the first SG1 block with 261 homes, wants to pay £10,000 towards town centre art instead of putting a permanent artwork on the site. A sculpture in King George V Playing Fields is suggested.
The first homes in the SG1 town centre scheme will have no permanent artwork of their own. Instead, the developer has asked the council to accept £10,000 towards public art elsewhere in the town centre. The request covers Claxton House, the ten-storey block of 261 homes on the old Swingate House site.
The planning permission for SG1 says every phase must have a public art programme, approved and in place, before anyone moves in. That is Condition 65 of permission 19/00743/FPM, granted on 30 May 2023.
What the developer is asking for
Swingate Phase 1A LLP applied on 27 October, with Mace Group acting as its agent. The application, reference 26/00774/COND, asks the council as planning authority to agree that:
- the temporary artwork on the construction hoardings, plus a £10,000 contribution, counts as the public art for the first two phases, called 1AA and 1AB
- the money can go into the council’s town centre Arts and Heritage programme
- a new SG1 Artwork Strategy sets the framework for public art across the rest of the six-hectare site
The developer’s justification paper says the buildings and landscaping are “substantially advanced” and were not designed around an artwork. A piece added now “would risk appearing as a retrospective addition”, it argues. It also lists practical limits: pedestrian space, highway sight lines, servicing, land ownership and who would maintain it.
Where the money could go
The paper points to art already near the site. Stacked Stories is at the bus interchange, about 50 metres away, and Nala the Cat is on the adjoining ramp.
It says the council’s regeneration team has identified, in principle, a possible spot for a further sculpture in King George V Playing Fields. The £10,000 would go towards an artwork on the town’s Arts and Heritage Trail. The application does not commit it to that site.
Has the council already agreed?
The documents read two ways. The strategy, dated 15 August, says the planning authority “has accepted” the £10,000 for Phase 1A. The justification paper, filed with it, is written as a request. The register shows the application as awaiting decision.
The strategy also says any decision will be taken by the council as planning authority, “independently of its interests as landowner, investor or joint venture partner”. Mace is building SG1 in partnership with the council.
What it means for you
Every later SG1 phase still needs its own public art, the developer says. It says approval here “would therefore not establish a precedent” for paying money instead on later phases. Those phases include Plot J, set aside for a primary school.
The strategy’s theme for the whole site is “Stevenage: First New Town, Connected Futures”. It says public art should respond to the nearby Town Square, the Grade II listed Joyride sculpture and the Clock Tower.
Applications to discharge a condition are not normally put out to public consultation, but the documents are public on the planning register under 26/00774/COND. More on how the system works is on our Stevenage planning page.
Claxton House was topped out in January. The council’s regeneration site says it is named after Eric Claxton, a member of the Stevenage Development Corporation, and will have a commercial unit on the ground floor.
Sources
- Stevenage Borough Council planning register, 26/00774/COND, validated week beginning 26 October 2026: application form, “SG1 Artwork Strategy” (draft 4, 15 August 2026) and “Justification for the Proposed Public Art Approach for Phases 1AA and 1AB”, read 31 October 2026
- Stevenage Even Better, “Claxton House reaches new heights with topping out ceremony”, 26 January 2026, for the 261 homes, the name and the partnership with Mace